The I-17 Improvement Project Has Reached Its One-Year Mark. What’s Been Done So Far?

By Jessica Swarner

September 28, 2023

QUICK TAKES:

  1. It’s been one year since construction began on I-17. The project is expected to finish in 2025.

  2. It’ll add new lanes to the freeway between Anthem Way and Sunset Point, more space on 10 bridges, and a full replacement of two bridges.

  3. The freeway remains open, with lane restrictions and closures happening only overnight on weekdays. 

  4. Right now, workers are removing 1.7 million cubic yards of material from mountainsides, which will be incorporated into the new roadway.

The Arizona Department of Transportation’s Interstate 17 improvement project has hit its one-year mark since major construction began. The project is expected to finish in 2025, and will add new lanes to a 23-mile stretch of the freeway between Anthem Way and Sunset Point. 

Those new lanes will include two “flex lanes,” which can run either northbound or southbound based on traffic or road closures. The first of their kind in the Arizona highway system, the flex lanes will run along the existing southbound lanes for 8 miles between Black Canyon City and Sunset Point. 

I  project area map Web Edit e

Map of I-17 improvement project (Arizona Department of Transportation graphic)

The current plan is for flex lanes to service northbound traffic from Monday through Saturday, and southbound traffic on Sundays. More information is available here

The I-17 improvement project also includes the widening of 10 bridges, and the full replacement of two bridges. 

What’s Been Done So Far? 

This past year was largely used for rock blasting and earthworking, which is the process of moving soil to change the level of land, according to ADOT. This work will continue into next year. 

ADOT officials said that workers are removing 1.7 million cubic yards of material from mountainsides and moving it to another area, to be worked into the project’s new roadway. 

Some of that material is already being used as a base for paving the southern lanes between Anthem Way and Table Mesa Road. The paving—which requires four different layers—started this summer and will continue into next year.  

The agency noted that the freeway has stayed open during this time of construction, with lane restrictions and closures only happening overnight on weekdays. The stretch of freeway being worked on sees more than 1 million travelers a year, according to ADOT. 

Sign up on ADOT’s website to receive email updates about the project. 

Subscribe to The Copper Courier’s daily newsletter! We keep it 💯—just like the temperature.

Author

CATEGORIES: Uncategorized

Support Our Cause

Thank you for taking the time to read our work. Before you go, we hope you'll consider supporting our values-driven journalism, which has always strived to make clear what's really at stake for Arizonans and our future.

Since day one, our goal here at The Copper Courier has always been to empower people across the state with fact-based news and information. We believe that when people are armed with knowledge about what's happening in their local, state, and federal governments—including who is working on their behalf and who is actively trying to block efforts aimed at improving the daily lives of Arizona families—they will be inspired to become civically engaged.

Camaron Stevenson
Camaron Stevenson, Founding Editor
Your support keeps us going
Help us continue delivering fact-based news to Arizonans
Related Stories
Share This